Alhamdulillah, we managed to went thru all the difficulties especially for OLPT project. Below are the activity summary :
1. Olak Lampit 275kV/132kV extension job -
i. Successfully converted existing SAT250 HMI to new SICAM 230 HMI with :
a. The first ever in the world have done redundancy SK mode + AK mode using ethernet. bye bye token ring. (we congratulate our SAT God a.k.a mr. honda for your effortless try & error)
b. delivered 8 bays of 132kV plus 2 bays of 275kV.
c. Do design, development, fix existing bugs and commissioning (FAT & SAT)
2. Upgrade & rectification of SAT 250 HMI system for Tenaga Nasional Berhad Substation :
i. Our Unix God a.k.a tunbendahara managed to to install and configure Sun Solaris x86 7 on Pentium 4.
So now SAT 250 user is able to get high performance machine to run SAT 250.
List of Project :
a. PMU Yong Peng - Upgrade SAT 250 HMI to Pentium 4 2.8 with 512MB RAM & fix all bugs
b. PMU Kinta Valley - Bring UP & Upgrade SAT 250 HMI to Pentium 4 2.8 with 1GB RAM & fix all bugs
c. NUR CCR - Bring UP & Upgrade SAT 250 HMI to Pentium 4 2.8 with 1GB RAM & fix all bugs
d. NUR EAST - Bring UP & Upgrade SAT 250 HMI to Pentium 4 2.8 with 1GB RAM & fix all bugs
e. NUR CCR, EAST, SOUTH, PMU - fix and restore respective AK SLC to work properly
f. PMU SJTC - Bring UP & Upgrade SAT 250 HMI to Pentium 4 2.8 with 1GB RAM & fix all bugs
3. SAT 230 related job :
a. PMU Sungkai - Bring UP & Upgrade SAT 230 HMI to Pentium Dual Core with 1GB RAM & fix all bugs